The Karachi Water and Sewerage Corporation (KWSC) has completed its annual maintenance work at the Dhabeji pumping station and says water supply has been restored across the city. However, many areas, including Landhi, Korangi, Malir and Shah Faisal towns, were still without water for a third consecutive day on Sunday.

Maintenance Work Completed

KWSC said the maintenance began on November 13 and created a shortfall of around 130 million gallons per day in water supply. On Sunday, the corporation announced that all 21 pumps at the Dhabeji pumping station are now operational.

Repairs Carried Out

According to a KWSC spokesperson, the following work was completed during the annual maintenance operation:

  • Repairs to water pipelines at Dhabeji, Pipri, Shahrah-i-Bhutto and the Haleji conduits
  • Installation of a new 60-inch-diameter valve at the Dhabeji pumping station
  • Repairs to all pump houses at the Pipri pumping station
  • Replacement of a 150-foot-long water pipeline along Shahrah-i-Bhutto
  • Repair of a leakage in the Haleji conduit

Water Supply in Affected Areas

KWSC said supply to Landhi, Korangi, Malir and Shah Faisal towns is being gradually brought back to normal. The corporation did not give a time frame for when normal supply would return.

The report was published in Dawn on November 16, 2026.