Project Cost Increases to Rs8 Billion
The expansion, restoration and renovation project at the shrine of Data Ganj Bakhsh Ali Hajveri in Lahore now carries a revised budget of Rs8 billion, up by Rs2 billion from the earlier estimate. The Punjab government has set June 2027 as the new completion deadline, pushing back the original 2024 target.
Reasons for Delay
Officials cite three main factors behind the schedule slip:
- Administrative lapses during early phases
- Design changes to handle growing visitor numbers
- Legal proceedings to reclaim residential and commercial properties around the shrine
The Auqaf Department has now secured possession of the required land, and construction is proceeding in phases.
Construction Accelerated
All 21 CNC machines deployed for the project have been ordered to remain operational. Previously only four to six machines were working, which slowed progress. Work is now continuing in multiple shifts around the clock.
A joint committee with representatives from the Auqaf Department, NESPAK and construction agencies has been formed to speed up decorative work, including restoration of arches, latticework and calligraphy.
Immediate Repairs Ordered
The government has directed prompt repair of cracks in the green tiles of the main dome and the white tiles of eight smaller domes.
New Facilities in Revised Plan
The expanded design includes:
- Larger courtyard with separate space for male and female visitors
- Basement parking facilities
- Underground passage connecting the main road directly to the shrine complex
- Modern langar facility for free meal distribution
Golden Door to Be Relocated
The golden door installed during former prime minister Zulfikar Ali Bhutto's tenure will be moved to allow further courtyard expansion. It will be refurbished and reinstalled at a new position.
Auqaf Director General Hafiz Aneesur Rehman said the budget increased due to changing requirements and the need to provide better facilities for the growing number of visitors.
Coordination Among Agencies
The provincial government has directed the Water and Sanitation Agency (WASA), the Traffic Engineering and Transport Planning Agency (TEPA) and NESPAK to expedite their respective components. Additional funds have been released for the project.